Our Project
Phase 1: a lean library, built to open quickly.
A lean, functional mabati-and-wood structure on community-donated land, with shelving for up to 10,000 books, seating for 100 users, and a small librarian's office with basic security, ventilation and lighting.


Facility
What Phase 1 includes
Each component below maps to a Concept Note budget line. All images are proposals — construction progress is not claimed.
Site preparation
Minor groundwork on the community-donated site; boundaries confirmed and the plot prepared for construction. KES 40,000.

Mabati-and-wood structure
A secure, affordable structure consistent with low-cost building options widely used in rural Kenya. KES 220,000.
Roofing, doors & windows
Weatherproof roofing with doors, windows and basic finishing for security, ventilation and daylight. KES 90,000.
Shelving for 10,000 books
Sturdy shelving organized for children, youth and adult collections, ready to grow from the first 1,000 books. KES 60,000.

Seating for 100 users
Reading and study seating for pupils, students and community members, including evening and weekend use. KES 45,000.

Librarian's office
A small administrative office for the librarian, cataloguing and basic administration. KES 25,000.
Lighting & fittings
Basic lighting and fittings so the space is usable and welcoming, with solar options for evening study. KES 10,000.
Security
Basic security for the building, books and users — doors, locks and site arrangements from the outset.
Launch preparation
Community launch and opening activities, then reading clubs, weekend study sessions and holiday programmes. KES 5,000.
Budget
Phase 1 budget — KES 500,000 ceiling
A lean first phase focused on functionality and early access. Donated land, the first 1,000 books (terms to be confirmed) and partner support keep the project achievable.
| Budget item | Cost (KES) |
|---|---|
| Site preparation and minor groundwork | 40,000 |
| Mabati-and-wood structure | 220,000 |
| Roofing, doors, windows and basic finishing | 90,000 |
| Shelving for up to 10,000 books | 60,000 |
| Seating for 100 users | 45,000 |
| Small office setup | 25,000 |
| Basic lighting and fittings | 10,000 |
| Community launch and opening activities | 5,000 |
| Contingency | 5,000 |
| Total | 500,000 |
Timeline
Implementation timeline
Aug 2026
Community mobilization, committee formation & site confirmation
Aug – Sep 2026
Resource mobilization & partner coordination
Sep 2026
Phase 1 construction (mabati-and-wood structure)
Sep 2026
Book stocking, cataloguing & staff recruitment
7 Oct 2026 (planned)
Official launch & activation of reading programmes
Ongoing from Oct 2026
Monitoring, review & sustainability planning
Long-term vision
Future phases may upgrade the structure with masonry, expand the collection toward and beyond 10,000 books, introduce ICT infrastructure and online learning access, and host more structured community learning activities as resources become available. Full functionality is estimated at KES 4,300,000 for a 144 sqm facility.
Monitoring
- Construction milestones against workplan and budget
- Books catalogued, available and circulated
- Membership, daily attendance and circulation records
- Reading-club and study-session participation
- Annual sustainability and growth review