Our Project

Phase 1: a lean library, built to open quickly.

A lean, functional mabati-and-wood structure on community-donated land, with shelving for up to 10,000 books, seating for 100 users, and a small librarian's office with basic security, ventilation and lighting.

Launch planned: 7 October 2026Community land donated
Different views of the proposed UCReCENT library building
Proposed building — different views (architectural rendering, not the built facility)
Interior reading and seating area of the proposed library
Proposed reading and seating area (architectural rendering)

Facility

What Phase 1 includes

Each component below maps to a Concept Note budget line. All images are proposals — construction progress is not claimed.

Site preparation

Minor groundwork on the community-donated site; boundaries confirmed and the plot prepared for construction. KES 40,000.

Mabati-and-wood structure

A secure, affordable structure consistent with low-cost building options widely used in rural Kenya. KES 220,000.

Roofing, doors & windows

Weatherproof roofing with doors, windows and basic finishing for security, ventilation and daylight. KES 90,000.

Shelving for 10,000 books

Sturdy shelving organized for children, youth and adult collections, ready to grow from the first 1,000 books. KES 60,000.

Seating for 100 users

Reading and study seating for pupils, students and community members, including evening and weekend use. KES 45,000.

Librarian's office

A small administrative office for the librarian, cataloguing and basic administration. KES 25,000.

Lighting & fittings

Basic lighting and fittings so the space is usable and welcoming, with solar options for evening study. KES 10,000.

Security

Basic security for the building, books and users — doors, locks and site arrangements from the outset.

Launch preparation

Community launch and opening activities, then reading clubs, weekend study sessions and holiday programmes. KES 5,000.

Budget

Phase 1 budget — KES 500,000 ceiling

A lean first phase focused on functionality and early access. Donated land, the first 1,000 books (terms to be confirmed) and partner support keep the project achievable.

Phase 1 budget breakdown
Budget itemCost (KES)
Site preparation and minor groundwork40,000
Mabati-and-wood structure220,000
Roofing, doors, windows and basic finishing90,000
Shelving for up to 10,000 books60,000
Seating for 100 users45,000
Small office setup25,000
Basic lighting and fittings10,000
Community launch and opening activities5,000
Contingency5,000
Total500,000

Timeline

Implementation timeline

  1. Aug 2026

    Community mobilization, committee formation & site confirmation

  2. Aug – Sep 2026

    Resource mobilization & partner coordination

  3. Sep 2026

    Phase 1 construction (mabati-and-wood structure)

  4. Sep 2026

    Book stocking, cataloguing & staff recruitment

  5. 7 Oct 2026 (planned)

    Official launch & activation of reading programmes

  6. Ongoing from Oct 2026

    Monitoring, review & sustainability planning

Long-term vision

Future phases may upgrade the structure with masonry, expand the collection toward and beyond 10,000 books, introduce ICT infrastructure and online learning access, and host more structured community learning activities as resources become available. Full functionality is estimated at KES 4,300,000 for a 144 sqm facility.

Monitoring

  • Construction milestones against workplan and budget
  • Books catalogued, available and circulated
  • Membership, daily attendance and circulation records
  • Reading-club and study-session participation
  • Annual sustainability and growth review